[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258405":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":13},1258405,842,1,"单选题","关于法律、法规和政策变化类合同价款调整，下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工、材料和工程设备等有关价格的变化已包含在物价波动事件的调价公式中时，合同价款不予调整",true,{"key":16,"text":17,"correct":18},"B","人工、材料和工程设备等有关价格的变化已包含在物价波动事件的调价公式中时，合同价款应予调整",false,{"key":20,"text":21,"correct":18},"C","人工、材料和工程设备等有关价格的变化已包含在物价波动事件的调价公式中时，合同价款调整由承发包双方协调解决",{"key":23,"text":24,"correct":18},"D","人工、材料和工程设备等有关价格的变化已包含在物价波动事件的调价公式中时，合同价款调整应由造价管理单位确定",{"id":6,"name":26,"category":27,"favorite":28},"(土建施工)专业管理实务 岗位知识","建筑工程",0]