[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258404":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258404,842,1,"单选题","施工项目成本控制的依据不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程承包合同",false,{"key":16,"text":17,"correct":18},"B","施工组织设计",true,{"key":20,"text":21,"correct":14},"C","进度报告",{"key":23,"text":24,"correct":14},"D","施工成本计划","施工项目成本控制的依据包括工程承包合同，进度报告和施工成本计划。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]