[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258403":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258403,842,1,"单选题","在施工合同履行期间由不可抗力造成的损失费用，下列应由承包人承担的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人的工地资产",false,{"key":16,"text":17,"correct":18},"B","因工程损害导致承包人人员伤亡",true,{"key":20,"text":21,"correct":14},"C","工程清理、修复费用",{"key":23,"text":24,"correct":14},"D","发包人要求赶工的赶工费用","在施工合同履行期间由不可抗力造成的损失费用，下列应由承包人承担的是因工程损害导致承包人人员伤亡。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]