[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258402":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258402,842,1,"单选题","根据索赔的目的和要求不同，可以将工程索赔分为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同规定的索赔和非合同规定的索赔",false,{"key":16,"text":17,"correct":18},"B","工期索赔和费用索赔",true,{"key":20,"text":21,"correct":14},"C","工程索赔和商务索赔",{"key":23,"text":24,"correct":14},"D","单项索赔和总索赔","1）根据索赔的目的和要求不同，可以将工程索赔分为工期索赔和费用索赔。2）根据索赔事件的性质不同，可以将工程索赔分为工程延误索赔、加速施工索赔、工程变更索赔、合同终止索赔、不可预见的不利条件索赔、不可抗力事件的索赔、其他索赔。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]