[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258400":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258400,842,1,"单选题","施工成本控制的依据不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程承包合同",false,{"key":16,"text":17,"correct":14},"B","进度报告",{"key":19,"text":20,"correct":21},"C","施工图",true,{"key":23,"text":24,"correct":14},"D","施工成本计划","施工成本控制的依据：①工程承包合同；②施工成本计划；③进度报告；④工程变更。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]