[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258399":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258399,842,1,"单选题","承包人在施工中提出的合理化建议涉及对设计图纸的更改，但未经工程师同意，由此发生的费用应用由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","发包人与承包人共同",{"key":23,"text":24,"correct":14},"D","承包人与工程师共同","承包人在施工中提出的合理化建议涉及对设计图纸的更改，但未经工程师同意，由此发生的费用应用由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]