[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258398":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1258398,842,1,"单选题","我国现行工程变更价款的确定方法不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同中已有适用于变更工程的价格，按合同已有的价格变更合同价款",false,{"key":16,"text":17,"correct":14},"B","合同中只有类似于变更工程的价格，可以参照类似价格变更合同价款",{"key":19,"text":20,"correct":14},"C","合同中没有适用或类似于变更工程的价格，由承包人提出适当的变更价格，经工程师确认后执行",{"key":22,"text":23,"correct":24},"D","施工合同条件下工程变更的估价",true,"《建设工程施工合同（示范文本）》约定的工程变更价款的确定方法如下：合同中已有适用于变更工程的价格，按合同已有的价格变更合同价款；合同中只有类似于变更工程的价格，可以参照类似价格变更合同价款；合同中没有适用或类似于变更工程的价格，由承包人提出适当的变更价格，经工程师确认后执彳了。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]