[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258393":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258393,842,1,"单选题","某工程包含甲乙两个子项工程，合同约定：甲项的全费用综合单价为200元\u002F㎡，乙项的综合单价为180元\u002F㎡；进度按月计算，第一个月实际完成甲项为700㎡，乙项完成500㎡气则本月应支付的工程款为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":18},"B","23",true,{"key":20,"text":21,"correct":14},"C","25",{"key":23,"text":24,"correct":14},"D","30","甲乙两个子项工程，合同约定：甲项的全费用综合单价为200元\u002F㎡，乙项的综合单价为180元\u002F㎡；进度按月计算，第一个月实际完成甲项为700㎡，乙项完成500㎡气则本月应支付的工程款为23万元。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]