[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258391":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1258391,842,1,"单选题","工程项目成本控制不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施费的控制",true,{"key":16,"text":17,"correct":18},"B","材料费的控制",false,{"key":20,"text":21,"correct":18},"C","人工费的控制",{"key":23,"text":24,"correct":18},"D","管理费的控制","工程项目成本控制主要从四个方面进行控制：①材料费的控制；②人工费的控制；③机械费的控制；④管理费的控制。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]