[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258389,842,1,"单选题","关于工期延误期间合同价款调整的特殊处理，说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人原因引起的工期延误.期间法律法规发生变化.合同价款给予调整",false,{"key":16,"text":17,"correct":18},"B","承包人原因引起的工期延误.期间法律法规发生变化.合同价款增加的.价款不予调整",true,{"key":20,"text":21,"correct":14},"C","承包人原因引起的工期延误.期间法律法规发生变化.合同价款减少的.价款不予调整",{"key":23,"text":24,"correct":14},"D","承包人原因引起的工期延误.期间法律法规发生变化.无论合同价款增加或减少.价款均不予调整","由于承包人原因导致的工期延误，在工程延误期间国家的法律、行政法规和相关政策发生变化引起的工程造价的变化，造成合同价款增加的，合同价款不予调整；造成合同价款减少的，合同价款予以调整。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]