[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258388":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258388,842,1,"单选题","工程变更的范围和内容不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","改变已批准的施工工艺或顺序",false,{"key":16,"text":17,"correct":14},"B","改变合同工程的基线、标高、位置或尺寸",{"key":19,"text":20,"correct":21},"C","施工合同中包含的工作内容，施工单位遗漏施工的",true,{"key":23,"text":24,"correct":14},"D","为完成工程需要追加的额外工作","工程变更的范围和内容包括改变已批准的施工工艺或顺序，改变合同工程的基线、标高、位置或尺寸和为完成工程需要追加的额外工作。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]