[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258386,842,1,"单选题","工序施工条件控制，是指对工序施工活动的（）进行有效控制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","A合同条件和法规条件",false,{"key":16,"text":17,"correct":14},"B","B工艺顺序和组织条件",{"key":19,"text":20,"correct":21},"C","C投人要素和环境条件",true,{"key":23,"text":24,"correct":14},"D","D工期条件和赶工措施","工序施工条件控制，是指对工序施工活动的投人要素和环境条件进行有效控制。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]