[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258342":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1258342,842,1,"单选题","组织流水施工时，时间参数不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","流水节拍",false,{"key":16,"text":17,"correct":14},"B","流水步距",{"key":19,"text":20,"correct":14},"C","工期",{"key":22,"text":23,"correct":24},"D","施工段",true,"时间参数包括：流水节拍、流水步距、平行搭接时间、技术与组织间歇时间、工期等。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]