[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258340":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1258340,842,1,"单选题","施工进度计划在编制时，工程量计算应注意很多事项，其中不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","划分的施工段数",true,{"key":16,"text":17,"correct":18},"B","工程量的计量单位",false,{"key":20,"text":21,"correct":18},"C","采用的施工方法",{"key":23,"text":24,"correct":18},"D","正确取用计价文件中的工程量","工程量计算时应注意的事项有：①工程量的计量单位；②采用的施工方法；③正确取用计价文件中的工程量。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]