[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258332":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1258332,842,1,"单选题","横道图进度计划中的横道线，不能结合时间坐标来表示项目各项工作之间的（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","开始时间",false,{"key":16,"text":17,"correct":14},"B","持续时间",{"key":19,"text":20,"correct":14},"C","先后顺序",{"key":22,"text":23,"correct":24},"D","资源消耗情况",true,"横道图进度计划中的横道线，不能结合时间坐标来表示项目各项工作之间的资源消耗情况。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]