[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258330,842,1,"单选题","关于控制性施工进度计划作用的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","论证施工总进度计划目标",false,{"key":16,"text":17,"correct":14},"B","分解施工总进度目标",{"key":19,"text":20,"correct":21},"C","不能作为施工进度动态控制的依据",true,{"key":23,"text":24,"correct":14},"D","编制实施性进度计划的依据","控制性施工进度计划能作为施工进度动态控制的依据",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]