[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258329":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1258329,842,1,"单选题","某基础混凝土浇筑需劳动量为1200个工日，划分为劳动量相等的3个施工段组织流水施工，每天采用两班制，每段投人的人工数为40个工日，其流水节拍值为（ ）d。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",true,{"key":16,"text":17,"correct":18},"B","8",false,{"key":20,"text":21,"correct":18},"C","10",{"key":23,"text":24,"correct":18},"D","15","1200\u002F3=400400\u002F40*2=5",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]