[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258328":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258328,842,1,"单选题","组织流水施工时，空间参数不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工层数",false,{"key":16,"text":17,"correct":18},"B","流水步距",true,{"key":20,"text":21,"correct":14},"C","工作面",{"key":23,"text":24,"correct":14},"D","施工段数","空间参数主要有：工作面、施工段数、施工层数。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]