[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258327":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258327,842,1,"单选题","某基础工程划分4个施工过程（挖基槽、垫层施工、混凝土浇筑、回填土），每个施工过程分为5个施工段，流水节拍均为3d，要求在混凝土浇筑2d后才能进行回填土施工，该工程的流水施工工期为（ ）d。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","39",false,{"key":16,"text":17,"correct":14},"B","29",{"key":19,"text":20,"correct":21},"C","26",true,{"key":23,"text":24,"correct":14},"D","14","节奏流水施工工期计算公式为：（5+4-1）×3-1+3=26d。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]