[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258326":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258326,842,1,"单选题","组织流水施工时，施工队组数大于施工过程数的流水方式是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","A等节奏流水",false,{"key":16,"text":17,"correct":14},"B","B异步距异节奏流水",{"key":19,"text":20,"correct":21},"C","C等步距异节奏流水",true,{"key":23,"text":24,"correct":14},"D","D无节奏流水","组织流水施工时，施工队组数大于施工过程数的流水方式是等步距异节奏流水。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]