[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258324":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1258324,842,1,"单选题","在拟建工程任务紧迫、工作面允许以及资源保证供应的条件下，可以组织（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","平行施工",true,{"key":16,"text":17,"correct":18},"B","顺序施工",false,{"key":20,"text":21,"correct":18},"C","流水施工",{"key":23,"text":24,"correct":18},"D","依次施工","在拟建工程任务紧迫、工作面允许以及资源保证供应的条件下，可以组织平行施工。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]