[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258322":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1258322,842,1,"单选题","某工程计划中A工作的持续时间为5天，总时差为8天，自由时差为4天。如果A工作实际进度拖延13天，则会影响工程计划工期（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","13",false,{"key":16,"text":17,"correct":14},"B","8",{"key":19,"text":20,"correct":14},"C","9",{"key":22,"text":23,"correct":24},"D","5",true,"首先它有总时差，若计划工期等于计算工期的话，它一定不是处于关键线路上。对总工期而言，会拖延13-8=5天。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]