[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258319":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258319,842,1,"单选题","绘制施工进度计划横道图时，首先应确定（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","流水方式",false,{"key":16,"text":17,"correct":14},"B","搭接方法",{"key":19,"text":20,"correct":21},"C","主导施工过程",true,{"key":23,"text":24,"correct":14},"D","流水节拍","绘制施工进度计划横道图时，首先应确定主导施工过程。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]