[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258318":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1258318,842,1,"单选题","分析进度计划偏差影响时，若工作的进度偏差大于该工作的总时差，则此偏差（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对后续工作和总工期都有影响",true,{"key":16,"text":17,"correct":18},"B","对后续工作有影响，对总工期无影响",false,{"key":20,"text":21,"correct":18},"C","对后续工作无影响，对总工期有影响",{"key":23,"text":24,"correct":18},"D","对后续工作和总工期都无影响","分析进度计划偏差影响时，若工作的进度偏差大于该工作的总时差，则此偏差对后续工作和总工期都有影响。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]