[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258317,842,1,"单选题","下列关于双代号网络图的绘制规则的说法中，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","双代号网络图必须正确表达逻辑关系",false,{"key":16,"text":17,"correct":18},"B","网络图中允许出现循环线路",true,{"key":20,"text":21,"correct":14},"C","网络图中不允许出现代号相同的箭线",{"key":23,"text":24,"correct":14},"D","严禁在网络图中出现没有箭尾节点的箭线和没有箭头节点的箭线","双代号网络图的绘制规则：①双代号网络图必须正确表达逻辑关系；②网络图中不允许出现循环线路；③网络图中不允许出现代号相同的箭线；④在一个网络图中只允许有一个起点节点和一个终点节点；⑤严禁在网络图中出现没有箭尾节点的箭线和没有箭头节点的箭线；⑥网络图中不允许出现双向箭头、无箭头或倒向的线；⑦绘制网络图时，应避免箭线交叉等。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]