[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258315":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258315,842,1,"单选题","关于采用增减工作范围方法调整施工进度计划，下列说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不得打乱原计划的逻辑关系",false,{"key":16,"text":17,"correct":14},"B","应重新计算时间参数",{"key":19,"text":20,"correct":21},"C","局部逻辑关系不能调整",true,{"key":23,"text":24,"correct":14},"D","应考虑对原网络计划的影响","局部逻辑关系可以调整。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]