[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258314":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258314,842,1,"单选题","施工进度计划跟踪检查通常可以确定每月、半月、旬或周进行一次。若在施工中遇到天气、资源供应等不利因素的严重影响，检查间隔时间可临时（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增长",false,{"key":16,"text":17,"correct":18},"B","缩短",true,{"key":20,"text":21,"correct":14},"C","不变",{"key":23,"text":24,"correct":14},"D","不能确定","施工进度计划跟踪检查通常可以确定每月、半月、旬或周进行一次。若在施工中遇到天气、资源供应等不利因素的严重影响，检查间隔时间可临时缩短。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]