[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258312":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1258312,842,1,"单选题","（ ）是指将在项目实施中检查实际进度收集的信息，经整理后直接用横道线并标于原计划的横道线处，进行直观比较的方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横道图比较法",true,{"key":16,"text":17,"correct":18},"B","S型曲线比较法",false,{"key":20,"text":21,"correct":18},"C","香蕉型曲线比较法",{"key":23,"text":24,"correct":18},"D","前锋线法","横道图比较法是指将在项目实施中检查实际进度收集的信息，经整理后直接用横道线并标于原计划的横道线处，进行直观比较的方法。S型曲线比较法，是以横坐标表示进度时间，纵坐标表示累计完成任务量，而绘制出一条按计划时间累计完成任务量的S型曲线，将施工项目的各检查时间实际完成的任务量与S型曲线进行实际进度与计划进度相比较的一种方法。前锋线法是通过实际进度前锋线与原进度计划中各工作箭线交点的位置来判断工作实际进度与计划进度的偏差，进而判定该偏差对后续工作及总工期影响程度的一种方法。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]