[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258310":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258310,842,1,"单选题","下列施工过程中，必须划人流水施工过程的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","加工厂生产各种预制构件",false,{"key":16,"text":17,"correct":14},"B","各种材料及构件、配件、半成品的运输",{"key":19,"text":20,"correct":21},"C","直接在工程对象上操作的施工过程",true,{"key":23,"text":24,"correct":14},"D","大型施工机具安置及脚手架搭设","直接在工程对象上操作的施工过程必须划人流水施工过程",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]