[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258308":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1258308,842,1,"单选题","在组织流水施工时，划分施工过程不需考虑的因素是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工方案及工程结构",false,{"key":16,"text":17,"correct":14},"B","劳动组织及劳动量大小",{"key":19,"text":20,"correct":14},"C","施工过程内容和工作范围",{"key":22,"text":23,"correct":24},"D","项目管理能力的强弱",true,"组织流水施工时，划分施工过程不需考虑的因素是项目管理能力的强弱。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]