[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258307":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258307,842,1,"单选题","双代号网络图中，虚箭线表示（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作的持续时间",false,{"key":16,"text":17,"correct":14},"B","资源的消耗",{"key":19,"text":20,"correct":21},"C","工作之间的逻辑关系",true,{"key":23,"text":24,"correct":14},"D","非关键工作","双代号网计划中，只表示前后相邻工作之间的逻辑关系，既不占用时间，也不耗用资源的虚拟的工作称为虚工作。虚工作用虚箭线表示。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]