[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258200":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1258200,841,3,"判断题","计日工适用的零星工作是指工程量清单中有相应项目的额外工作。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"计日工适用的所谓零星项目或工作一般是指合同约定之外的或者因变更而产生的、工程量清单中没有相应项目的额外工作，尤其是那些难以事先商定价格的额外工作。计日工应列出项目名称、计量单位和暂估数量。",{"id":6,"name":21,"category":22,"favorite":23},"(土建施工)基础知识","建筑工程",0]