[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257918":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1257918,841,2,"多选题","工程量清单的项目设置规则是为了统一工程量清单的（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目名称",true,{"key":16,"text":17,"correct":14},"B","项目编码",{"key":19,"text":20,"correct":14},"C","计量单位",{"key":22,"text":23,"correct":24},"D","措施费计算规则",false,{"key":26,"text":27,"correct":14},"E","项目特征","ABCE","工程量清单的项目设置规则是为了统一工程量清单的项目名称，项目编码，计量单位和项目特征。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)基础知识","建筑工程",0]