[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257911":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1257911,841,2,"多选题","工程量的计算依据包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","施工图纸",true,{"key":16,"text":17,"correct":14},"B","设计变更",{"key":19,"text":20,"correct":14},"C","图纸答疑",{"key":22,"text":23,"correct":14},"D","会审记录",{"key":25,"text":26,"correct":27},"E","经济核算",false,"ABCD","工程量的计算依据：（1）施工图纸及设计说明、相关图集、设计变更、图纸答疑、会审记录等；工程施工合同、招标文件的商务条款；（2）工程施工合同、招标文件的商务条款。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)基础知识","建筑工程",0]