[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257900":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1257900,841,2,"多选题","工程定额计价方法与工程量清单计价方法的区别（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制工程量的主体不同",true,{"key":16,"text":17,"correct":18},"B","合同价格不同",false,{"key":20,"text":21,"correct":14},"C","单价与报价的组成不同",{"key":23,"text":24,"correct":14},"D","计价依据不同",{"key":26,"text":27,"correct":14},"E","适用阶段不同","ACDE","工程定额计价方法与工程量清单计价方法的区别：（1）两种模式最大的差别在于体现了我国建设市场发展过程中的不同定价阶段；（2）两种模式的主要计价依据及其性质不同；（3）编制工程量的主体不同；（4）单价与报价的组成不同；（5）适用阶段不同；（6）合同价格的调整方式不同；（7）工程量清单计价把施工措施性消耗单列并纳入了竞争的范畴。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)基础知识","建筑工程",0]