[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257896":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1257896,841,2,"多选题","在多层建筑施工中，要由下层向上层传递高程，一般采用（ ）来保证楼板面高度准确。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","利用皮数杆传递高程",true,{"key":16,"text":17,"correct":18},"B","水准仪传递高差",false,{"key":20,"text":21,"correct":14},"C","垂吊钢尺用水准仪法",{"key":23,"text":24,"correct":14},"D","利用钢尺自首层高程基准线直接丈量",{"key":26,"text":27,"correct":18},"E","吊锤球自首层控制线引测","ACD","在多层建筑施工中，要由下层向上层传递高程，一般采用利用皮数杆传递高程，垂吊钢尺用水准仪法，利用钢尺自首层高程基准线直接丈量来保证楼板面高度准确。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)基础知识","建筑工程",0]