[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257885":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1257885,841,2,"多选题","以下对轴线控制桩法叙述正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","可以控制标高",false,{"key":16,"text":17,"correct":18},"B","可以控制轴线位置",true,{"key":20,"text":21,"correct":14},"C","与龙门板法相比机械化施工时易破坏",{"key":23,"text":24,"correct":18},"D","轴线控制桩一般设置在基槽外2?4m处",{"key":26,"text":27,"correct":18},"E","轴线可以投测到附件的建筑物","BDE","轴线控制桩法：龙门板法占地大，使用的材料较多，施工时易被破坏，因此目前工程中一般采用轴线控制桩法。轴线控制桩一般设置在基槽外2?4m处，也可把轴线投测到附件的建筑物或构筑物上，做好标志，代替轴线控制桩。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)基础知识","建筑工程",0]