[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257882":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1257882,841,2,"多选题","下列关于建筑物高程控制的说法，符合规定的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建筑物高程控制，应采用水准测量。",true,{"key":16,"text":17,"correct":14},"B","附合路线闭合差，不应低于四等水准测量的要求。",{"key":19,"text":20,"correct":21},"C","水准点可设置在平面控制网的标桩或外围的固定地物上，不可单独埋设。",false,{"key":23,"text":24,"correct":14},"D","当场地高程控制点距离施工建筑物小于200m时，可直接利用",{"key":26,"text":27,"correct":21},"E","水准点的个数，不应少于4个","ABD","水准点可设置在平面控制网的标桩或外围的固定地物上，也可单独埋设。水准点的个数，不应少于3个",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)基础知识","建筑工程",0]