[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257867":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1257867,841,2,"多选题","下列关于涂饰工程施工工艺的说法中，有误的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工工艺流程为：基层处理→打底、批刮腻子→面层施涂→修理",false,{"key":16,"text":17,"correct":18},"B","混凝土与抹灰表面在施涂前应将基体或基层的缺棱掉角处、孔洞用1:2的水泥砂浆修补",true,{"key":20,"text":21,"correct":18},"C","外墙抗裂弹性腻子修补、填平时，待修补完成后，将抹灰面满刮外墙抗裂弹性腻子一遍，腻子批刮厚度为0.3～0.8mm",{"key":23,"text":24,"correct":18},"D","面层施涂滚涂大面时，用长度为15～20cm的长辊，以利于提高功效",{"key":26,"text":27,"correct":14},"E","底漆和乳胶漆施工适宜温度为0℃以上，未用完的底乳胶漆应加盖密封，并存放在阴凉通风处","BCD","涂饰工程施工工艺流程为：基层处理→打底、批刮腻子→面层施涂→修理。混凝土与抹灰表面在施涂前应将基体或基层的缺棱掉角处、孔洞用1:3的水泥砂浆（或用聚合物砂浆）修补。待水泥砂浆抹面干燥后，将其表面的孔洞、裂缝及凹坑等用外墙抗裂弹性腻子修补、填平，轻微的地方用刮刀嵌入腻子补齐，严重的地方用刮铲填充腻子找平。待腻子干燥后，用中号砂纸将其表面打磨平整，并及时清除粉尘。待修补完成后，将抹灰面满刮外墙抗裂弹性腻子一遍，腻子批刮厚度为0.2～0.5mm，同一方向往返刮。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)基础知识","建筑工程",0]