[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257646,841,1,"单选题","室内防水施工流程顺序正确的是",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","清理基层→防水材料进场复试→技术交底→结合层→细部附加层→防水层→试水试验",false,{"key":16,"text":17,"correct":14},"B","清理基层→技术交底→防水材料进场复试→结合层→细部附加层→防水层→试水试验",{"key":19,"text":20,"correct":21},"C","防水材料进场复试→技术交底→清理基层→结合层→细部附加层→防水层→试水试验",true,{"key":23,"text":24,"correct":14},"D","防水材料进场复试→清理基层→细部附加层→防水层→技术交底→结合层→试水试验","室内防水工程施工流程：防水材料进场复试一技术交底一清理基层一结合层—）细部附加层斗防水层斗试水试验。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]