[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257638,841,1,"单选题","土方开挖的顺序、方法必须与设计工况相一致，并遵循（ ）的原则。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","开槽支撑.先挖后撑.分层开挖.严禁超挖",false,{"key":16,"text":17,"correct":14},"B","开槽即挖.先挖后撑.一次开挖.严禁开挖",{"key":19,"text":20,"correct":21},"C","开槽支撑.先撑后挖.分层开挖.严禁超挖",true,{"key":23,"text":24,"correct":14},"D","开槽支撑.先撑后挖.一次开挖.适当超挖","此题比较简单，主要考核基坑工程施工时土方开挖应遵循的基本原则。根据《建筑地基基础工程施工质量验收规范》GB50202-2002第7.1.3条：土方开挖的顺序、方法必须与设计工况相一致，并遵循“开槽支撑，先撑后挖，分层开挖，严禁超挖”的原则。故本题正确选项应为“C．开槽支撑、先撑后挖、分层开挖、严禁超挖”。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]