[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1257622,841,1,"单选题","向当地城建档案管理部门移交工程竣工档案的责任单位是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":14},"B","分包单位",{"key":19,"text":20,"correct":14},"C","监理单位",{"key":22,"text":23,"correct":24},"D","建设单位",true,"本题考核建筑工程资料移交与归档责任的知识点，对有一定现场实践经验的考生来说，此题属业界常识，比较简单。根据《建筑工程资料管理规程》JGJ\u002FT185-2009第4.5.2条第5款之规定：建设单位应按国家有关法规和标准的规定向城建档案管理部门移交工程档案，并办理相关手续。有条件时，向城建档案管理部门移交的工程档案应为原件。所以，向城建档案管理部门移交工程竣工档案属建设单位责任。有很多项目的建设单位，都将该责任强行转嫁给施工单位，其实是错误的做法。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]