[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257605":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1257605,841,1,"单选题","施工组织设计的纲领性内容是（ ），施工组织设计的组成内容都应围绕其原则编制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工进度计划",false,{"key":16,"text":17,"correct":14},"B","施工管理计划",{"key":19,"text":20,"correct":14},"C","资源配置计划",{"key":22,"text":23,"correct":24},"D","施工部署",true,"施工部署是在对拟建工程的工程情况、建设要求、施工条件等进行充分了解的基础上，对项目实施过程涉及的任务、资源、时间、空间做出的统筹规划和全面安排。施工部署是施工组织设计的纲领性内蓉，施工进度计划、施工准备与资源配置计划，施工方法、施工现场平面布置和主要施工管理计划等施工组织设计的组成内容都应该围绕施工部署的原则编制。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]