[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257583":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1257583,841,1,"单选题","某公司施工6间相同的楼面，施工方法一样，均为放钢筋网片，支模板，浇筑混凝土三个过程，分别由指定的班组完成，每个班组在每间楼面施工时间均为2天，拟采用等节奏流水施工，则工期是（ ）天（不考虑工艺间歇）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","16",true,{"key":16,"text":17,"correct":18},"B","12",false,{"key":20,"text":21,"correct":18},"C","9",{"key":23,"text":24,"correct":18},"D","8","本工程施工段数m=6，施工过程n=3，流水节拍t=2，流水步距K=2，施工层数r=l，工期T=（m×r+n-l）×K=16。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]