[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257582,841,1,"单选题","建筑工程项目施工管理施工顺序正确的是",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","“先土建.后设备”“先准备.后开工”“先地下.后地上”“先结构.后装饰”“先主体.后围护”",false,{"key":16,"text":17,"correct":14},"B","“先地下.后地上”“先准备.后开工”“先土建.后设备”“先主体.后围护”“先结构.后装饰”",{"key":19,"text":20,"correct":21},"C","“先准备.后开工”“先地下.后地上”“先主体.后围护”“先结构.后装饰”“先土建.后设备”",true,{"key":23,"text":24,"correct":14},"D","“先地下.后地上”“先准备.后开工”“先主体.后围护”“先土建.后设备”“先结构.后装饰”","一般工程的施工顺序：“先准备、后开工”“先地下、后地上”“先主体、后围护”“先结构、后装饰”“先土建、后设备”。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]