[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257569,841,1,"单选题","基坑施工时遇到基坑坍塌迹象后，采取应急处理措施不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","采取水泥墙等重力式支护结构",false,{"key":16,"text":17,"correct":14},"B","发生管涌，可在支护墙前再打一排钢板桩，在钢板桩与支护墙闯进行注浆",{"key":19,"text":20,"correct":21},"C","对轻微流砂现象，可暂时不用采取措施",true,{"key":23,"text":24,"correct":14},"D","对较严重的流砂，应增加坑内降水措施","基坑施工时遇到基坑坍塌迹象后，应急处理措施有：（1）采取水泥墙等重力式支护结构，如果位移超过设计值应予以高度重视，做好位移监测，掌握发展趋势；（2）发生管涌，可在支护墙前再打一排钢板桩，在钢板桩与支护墙间进行注浆；（3）对轻微流砂现象，在基坑开挖后采用加快垫层浇筑或加厚垫层的方法“压住”流砂；对较严重的流砂，应增加坑内降水措施等。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]