[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257561":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1257561,841,1,"单选题","工程桩应进行承载力试验。对于地基基础设计等级为甲级或地质条件复杂，成桩质量可靠性低的灌注桩，应采用静载荷试验的方法进行检验，检验桩数不应少于总数的（ ），且不应少于3根。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","l%",true,{"key":16,"text":17,"correct":18},"B","0.03",false,{"key":20,"text":21,"correct":18},"C","0.05",{"key":23,"text":24,"correct":18},"D","0.1","对于地基基础设计等级为甲级或地质条件复杂，成桩质量可靠性低的灌注桩，应采用静载荷试验的方法进行检验，检验桩数不应少于总桩数的1%，且不少于3根。当总桩数少于50根时，不应少于2根。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]