[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257556":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1257556,841,1,"单选题","地面和水池的蓄水试验应达到（ ）h以上，墙面间歇淋水试验应达到30min以上，进行检验不渗漏。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","21",false,{"key":16,"text":17,"correct":14},"B","22",{"key":19,"text":20,"correct":14},"C","23",{"key":22,"text":23,"correct":24},"D","24",true,"地面和水池的蓄水试验应达到24h以上，墙面间歇淋水试验应达到30min以上进行检验不渗漏。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]