[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257552":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257552,841,1,"单选题","冬季填方每层铺土厚度应比常温施工时减少（ ），预留沉降量比常温时适当增加，土方中不得含冻土块及填土层受冻。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30%-35%",false,{"key":16,"text":17,"correct":14},"B","10%-25%",{"key":19,"text":20,"correct":21},"C","20%-25%",true,{"key":23,"text":24,"correct":14},"D","10%-20%","按照回填土的技术要求，冬季填方每层铺土厚度应比常温施工时减少20%~25%预留沉降量比常温时适当增加，土方中不得含冻土块及填土层受冻。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]