[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257547":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1257547,841,1,"单选题","吊顶工程施工中，主龙骨宜平行房间长向布置，分档位置线从吊顶中心向两边分，间距不宜大于（ ），并标出吊杆的固定点。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","600mm",false,{"key":16,"text":17,"correct":14},"B","900mm",{"key":19,"text":20,"correct":14},"C","1000mm",{"key":22,"text":23,"correct":24},"D","1200mm",true,"吊顶工程施工的工艺流程为：弹吊顶标高水平线一画主龙骨分档线一吊顶内管道、设备的安装、调试及隐蔽验收一吊杆安装一龙骨安装（边龙骨安装、主龙骨安装、次龙骨安装）一填充材料的设置一安装饰面板一安装收口、收边压条。在进行画主龙骨分档线的施工时，主龙骨宜平行房间长向布置，分档位置线从吊顶中心向两边分，间距不宜大于1200mm，并标出吊杆的固定点。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]